Northampton General Hospital – Talbot Butler Ward
Keith Barrow Heating & Plumbing Special Projects Ltd undertook a job on behalf of R Mclester Builders for the Talbot Ward (Cancer Ward) in Northampton's General Hospital.
This job consisted of supplying & installing all heating & plumbing, sanitary ware, fitting grab rails, w.c seats, shower seats, modifications to hot & cold water services, modifications to LTHW system, modifications to ventilation systems, refurb to air con systems, above ground drainage, supply & removal of fire hose reel & fire main & supplied & fitted all disabled facilities.
The project took 10 weeks which resulted in the Talbot Ward being closed down for that period of time.
Project Valuation: £37,630.87