Towcester Childrens Centre

Towcester Childrens Centre

Keith Barrow Heating & Plumbing Special Projects were proud to undertake a project on the behalf of SDC Special Projects for Towcester's Children Centre, based in Northamptonshire.

6th October 2010

Re:  Towcester Childrens Centre

 

We thank you for the opportunity to tender for the above works and are pleased to offer our quotation based on receipt of the following documentation:

Enquiry Letter Dated 21/09/10 ref: AL/dls/SP656

BSD Design Specification

Mechanical Services Drawings: - M-1100 Rev C1, 1101 Rev C1, 1201 Rev C1, 1401 Rev C1, 1501 Rev C1, 1601 Rev C1 drawing 1 + 2

PHP Architects Drawings

Project Particulars and M&E Preambles

Our price for carrying out this work has been evaluated using the documentation detailed above and would be for the sum of the following works detailed in the particular mechanical specification:

 1.0 - Preliminaries & site set up £500.00

2.0 - Strip out & enabling £Included

3.0 - hot & cold water services

3.1 - Pipework, valves & fittings £855.00

3.2 - Thermal insulation (trace heating where required) £150.00

3.3 - Mains cold water supply pipework £Included

3.4 - New water heater £463.00

4.0 - Above ground drainage

4.1 - Associated drainage pipework & sanitary ware installation only £580.00

5.0 - LTHW heating

5.1 - Provision & installation of new boiler and associated equipment £8,742.61

5.2 - Provision of new heat emitters £3,948.00

5.3 - Provision & installation of radiant panels £7,964.13

5.4 - Pipework, valves & fittings £2,879.51

5.5 - Thermal insulation £750.00

5.6 - Boiler controls & wiring (provisional sum, clarification required) £3,000.00

6.0 - Mechanical ventilation

6.1 - Supply & installation of ventilation systems £4,926.94

6.2 - Wiring of ventilation systems £excluded

7.0 - Gas pipework £Included

8.0 - Testing & commissioning £1,350.00

9.0 - Operating & maintenance manuals £300.00

11.0 - Contingency sum £6,000.00

Sub Total : £42,709.19

Main contractors discount 1 / 39th : £1,095.11

Total = £43,804.30

NB:- Gas pipework from meter installation only within plantroom.
NB:- Clarification is required on the controls package to be provided to the development.

To help you evaluate our quotation we wish to bring the following points to your attention:

 

Particular Specification Points

 

The above price does not include V.A.T.

No allowances have been made for any builders or electrical works.

Where required ventilation fans will be passed to the main contractor for installation within the structure

All loose controls will be passed to the Electrical Contractor for field wiring.

Ventilation has only been allowed to for the rooms identified in the Mechanical Services Specification.

No temporary gas or water supplies have been allowed for the duration of the project.

All new sanitary-ware to be provided free issue by the main contractor

All sealing of sanitary-ware is to be undertaken by the main contractor

No Lead works.

No decoration whatsoever

No white goods, connections only

To supply and install all the soil & vent and waste systems above slab only.

No rainwater.

Below Ground Drainage

24 hour/weekend working

Out of hours working for draining existing systems

Working Platforms above 3m

Cranage

No boxing in of pipework systems on show pendock etc... to be undertaken by the main contractor

Pricing against a detailed program of works from the M.C

Parking will be available on site

Welfare facilities will be made available on site

Special attendances for commissioning systems

 

Validity

 

This offer shall remain open for acceptance for a period of 6 weeks from the date of this tender.

We would require a minimum of 3 weeks notice from the date of written acceptance of this tender, or from receipt of such drawings and information as are agreed by us as being sufficient, to commence work on site.

Our tender is based upon our being able to complete the works within our unimpeded working time, provided that all drawings and information are supplied in compliance with a previously agreed programme and enabling us to proceed to the planned completion date.

 

Fixed Price

Our tender is fixed for the duration of the enclosed completion and acceptance period and would be subject to increased cost should these dates expire.

Bond

Our tender excludes any provision for a performance bond.

 

General Conditions

 

A          This tender does not include the cost of any Value Added Tax which may become chargeable on the work.

 

B          Our tender has been based upon free use of all facilities and unrestricted access being available to enable our works to be carried out during our

            standard working week of five days commencing 08.00 hours and finishing at 16.30 hours Monday to Friday.  Any deviation from this would result in an increase to our tender sum.

 

C          We have accepted and based our tender on the materials and information stated in the Tender Specification and Drawings.  Our responsibility covers only the procurement, installation, setting to work and commissioning of the equipment specified.

 

D          Where work has been described within the specification but not quantified or scheduled out, we have only

allowed for the extent detailed on the tender drawings. Any work executed within this category during the contract, which is not detailed on the tender drawings will become variations to our contract.

 

E        We have made no allowance for the provision of any samples, spares or factory witness tests

 

F          We have allowed for a 12 Month warranty period on parts and labour for all equipment supplied and installed by ourselves from the date of practical completion. This assumes that the system is maintained in accordance with manufacturer's instructions.

 

 

Attendance's

 

            The main contractor to provide the following attendances free of charge.  These may be in addition to attendance's given under our sub-contract:

 

  • 1) General Welfare facilities.
  • 2) Cutting, forming or leaving holes and chases in walls or floors as indicated on our builders work drawings or as marked on site as appropriate, together with making good of same. 
  • 3) Removal of all excess material and rubbish from a central location on site.
  • 4)Adequate safety lighting to be provided to all working areas and passage ways.
  • 5) Datum levels to be clearly marked for finished floor levels in each working area.
  • 6) Sufficient 110 volt electrical socket outlets to be provided in each work area for power for hand tools for all employees in order for us to comply with your programme.
  • 7) Fuel & water for testing, commissioning and site accommodation.
  • 8) Payment of all Statutory Authority charges.
  • 9) Protection of our installed equipment in vulnerable areas.
  • 10) Concreting or pointing of any description.
  • 11) Sealing around Sanitaryware with sealant.
  • 12)  Fire stopping and general making good.
  • 13) Only written variations to the contract works will be accepted with the price agreed prior to works being undertaken.

 

We trust that we have interpreted your requirement fully and that our quotation meets with your approval.  Should you have any queries regarding our submission please do not hesitate to contact us.

Assuring you of our best attention at all times.

 

Yours faithfully

For Keith Barrow HP (SP) Ltd

Legionella & chlorification of hot & cold water services, & provided certification to the same.
Carried out the installation & commissioning of Gas Boilers & registered with Gas Safe & Building Control.

Job Valuation: £44,000

Please see photographs attached

Posted Date: 29th Mar 2011

Towcester Childrens Centre
Towcester Childrens Centre
Towcester Childrens Centre
Towcester Childrens Centre
Towcester Childrens Centre
Towcester Childrens Centre
Towcester Childrens Centre